Manitoba Hydro has been given their Environmental Act Licence to build the Birtle Transmission Project and construction is slated to start this Spring.

The project is part of a long-term deal between Manitoba Hydro and SaskPower signed in October 2018 to provide up to 315 megawatts of hydroelectric power to Saskatchewan by 2022.

Starting at the Birtle station just south of the town, the transmission line will zig-zag west to Tantallon, Saskatchewan. Click here for a map of the Manitoba portion of the transmission line. More detailed maps can be found here.

Saskatchewan still relies heavily on coal-powered electricity and the Birtle Transmission Project will provide enough hydroelectric power for 82,000 homes.